Header manufacture and installation
we were called to a breakdown of a header leaking which turned out to be a lamating fracture on the steel body.
after speaking with the customer we were instructed to replace the failing valves,steam trap and manufacture a header to the same spec as before but with inspection blanks.
header was manufactured in 3 days to a high spec and then installed over a weekend to minimise intruption on the working plant.
Great work from the team at H&R!




New steam boiler install
This was a full installation with out clients already bought new boiler and design (model, p&id and specs)
all fabricated and installed by the team at H&R




plantroom for air source heat pumps
This install was for a carehome including manufacture of headers within a tight deadline.




cooling tower upgrade
a faulty motor diagnosed by site ended up been a full replacement of motors to the fans and electrical upgrade.




Mechanical installation for heating and decarbonisation
this project was for a major building contractor including heating, decarbonsation systems and cooling.
the project lasted multiple months with all fabrication and installation carried out to a high standard




gas meter installation
we installed a gas meter on behalf of a oven manufacture for there installation team to connect too